PEREZ, J.:
This petition for review assails the 15 January 2010 Decision1 and 13 July 2010 Resolution2 of the Court of Appeals in CA-G.R. SP No. 102007 which affirmed the Final Award rendered by the Construction Industry Arbitration Commission (CIAC) Arbitral Tribunal on 7 December 2007.
FACTUAL ANTECEDENTS
Petitioner B.F. Corporation (BFC) is a corporation engaged in general engineering and civil works construction. Petitioner Honorio H. Pineda (Pineda) is the President of BFC. Respondent Form-Eze Systems Inc. (Form-Eze) is a corporation engaged in highway and street construction.
On 29 August 2006, SM Prime Holdings, Inc. awarded the contract for general construction of the SM City-Marikina mall (the Project) to BFC whereby the latter undertook to supply materials, labor, tools, equipment and supervision for the complete construction of the Project.3 In turn, BFC engaged Form-Eze for the lease of formwork system and related equipment for and needed by the Project. Accordingly, five (5) contracts and two (2) letter-agreements were executed by the BFC, represented by its President Pineda, and Form-Eze, represented by its President, James W. Franklin. These contracts and their salient provisions are provided in the following table:
CONTRACT NO. 1: Contract for the Lease of the Equipment for the Beam and Slab Hardware for the Formwork on SM Marikina Mall Project dated 20 December 20064 | |
Obligations of Form-Eze |
|
Obligations of BFC |
|
Work Specifications | The amount of hardware to be furnished is sufficient to provide 7,000 contact square meters of formwork. |
Contract Price | Total contract amount for the equipment: 126,000 contact square meters (equipment to be used) x P225.00/contact square meter (cost per use of the hardware for forming the elevated beam and slab)= P28,350,000.00. |
Terms of Payment |
|
CONTRACT NO. 2: Contract for Stripping and Moving Form-Eze Systems Inc. Equipment from Location to Location on SM Marikina Mall Project dated 20 December 2006 5 | |
Obligations of Form-Eze |
|
Obligations of BFC |
|
Contract Price | Total contract amount for moving equipment: 126,000 x P50.00/contact square meter (cost for stripping and movement of the equipment, excluding cost of resetting to grade, cleaning plywood surfaces and applying release agent) P6,300,000.00. |
Terms of Payment |
|
CONTRACT NO. 3: Contract for Column Formwork on the SM Marikina Mall Project dated 20 December 20066 | |
Obligations of Form-Eze |
|
Obligations of BFC |
|
Terms of Payment |
|
CONTRACT NO. 4: Contract for the Lease of the Heavy Duty Galvanized Scaffold Frames and Related Accessories on SM Marikina Mall Project dated 29 January 20077 | |
Obligations of BFC |
|
Obligations of Form-Eze |
|
Agreement is contingent upon parties entering into an exclusive licensing agreement with BFC for the manufacture of Form-Eze equipment. | |
CONTRACT NO. 5: Contract for the Purchase and Lease of the Heavy Duty Galvanized X-Bracing on SM Marikina Mall Project dated 29 January 20078 | |
Obligations of BFC | Manufacture heavy duty galvanized x-bracing. |
Obligations of Form-Eze | Credit BFC with P400.00 per x-brace. If the x-bracing is not manufactured exactly as specified by Form-Eze, credit is P300.00 per x-brace. |
Agreement is contingent upon parties entering into an exclusive licensing agreement for the manufacturing of Form-Eze equipment. | |
MEMORANDUM OF AGREEMENT dated 5 January 20079 | |
BFC will manufacture Form-Eze equipment and will sell exclusively to Form-Eze. | |
LETTER-AGREEMENT dated 5 January 200710 | |
Changes to Contract No.4 | |
| |
On 30 March 2007, Form-Eze filed a Request for Arbitration11 before the CIAC. In its Complaint, Form-Eze alleged that BFC has an unpaid obligation amounting to P9,189,024.58; that BFC wanted to re-negotiate the equipment leases; and that it was not complying with the contractual and supplemental agreements in effect. Form-Eze prayed for the following relief:
- [For BFC] to pay the current monthly equipment rentals;
- Provisions made to guarantee the earned monthly equipment leased amounts are paid timely;
- To legislate provisions to ensure the lease contracts are not breached during the construction of the SM Marikina Mall;
- Provisions made to guarantee the performance of [BFC] for the manufacturing of the shoring equipment purchased by Form-Eze from BFC;
- Provisions made to guarantee the return of all Form-Eze equipment when the concrete structure is completed and all lost and damaged equipment has been paid for by [BFC]; and
- All cost related to Arbitration.12
In its Amended Answer with Counterclaim, BFC sought for reformation of Contract #1 to incorporate a provision that BFC shall deduct from said billing the cost of labor supplied by it for the fabrication and assembly of the forming system and for the stripping, cleaning, resetting thereof at the rate of P60.00 per man-hour. BFC also demanded the refund of P5,773,440.00 as expenses for the manufacture of additional hardware to complete the 7,000 square meters of formwork required in Contract #1. BFC explained that Form-Eze had only furnished 4,682.4 square meters of formwork.13
The CIAC appointed a 3-member Arbitral Tribunal (CIAC Arbitral Tribunal), composed of Atty. Custodio O. Parlade, Atty. Alfredo F. Tadiar and Engineer Romeo C. David, to adjudicate Form-Eze's claims.
Under the Terms of Reference, the parties made the following admissions:
- The existence of five contracts, a memorandum of agreement and a supplemental contract.
- BFC renegotiated Contract #1 but it did not result in a separate written contract.
- Under Contract #1, BFC is willing and ready to pay Form-Eze the amount of P3,515,003.59, which amount shall be deducted from the amount of the latter's claim.
- Under Contract BFC is willing and ready to pay Form-Eze the amount of P675,788.97, which amount shall be deducted from the amount of the latter's claim.
- BFC admits that it has the obligation to return to Form-Eze equipment furnished them under Contracts #1, 2, and 3, and all heavy duty galvanized scaffold frames and related accessories, heavy duty galvanized x-bracing and adjustable U-heads and base plates fabricated and manufactured by BFC under Contracts #4, 5 and letters dated 5 January 2007.14
The claims15 of the parties are summarized, as follow:
FORM-EZE'S CLAIMS As of 7/19/2007 From 7/20/2007 to end of contract based on agreed minimum contact sq.m. of 126,000 Arrears on Contract No.1
P26,310,476.29
- 3,515,003.5922,795,472.70 P11,489,523.71 Arrears on Contract No. 2
4,771,723.63
-675,788.974,095,934.66 1,528,276. 37 Arrears on Contract No.3 2,099,825.00 1,130,675.00 Arrears on Letter dated 1/5/07 740,600.00 483,000.00 P29,731,832.36 P14,631,475.08 Attorney's Fees 300,000.00____ TOTAL SUM IN DISPUTE P44,663,307.44
BFC's COUNTERCLAIM Cost of labor, helmet & expenses for x-bracing for the assembly of the form
system under Contract #1P 812,791.09 Cost of stripping, petroleum, oil, & helmet under Contract #2 1,391,086.02 Attorney's Fees 300,000.00 Total Counterclaims P2,503,877.11 TOTAL SUM IN DISPUTE P46,867,184.55
The total arbitration fees amounted to P616,393.73.
CIAC Arbitral Tribunal was tasked to resolve the following issues, to wit:
- Is Claimant entitled to its total claim of P34,284,996.41 representing the alleged arrear on equipment rental under Contract #1?
- Contract #1 - Provisions to guarantee the earned monthly equipment leased amounts are paid timely;
- Contract #1 - Provision to ensure that the lease contracts are not breached during the construction of the SM Marikina Mall;
- Contracts #4 and 5 - Provision to guarantee the performance of [BFC] for the manufacturing of the shoring equipment purchased by Form-Eze from BF Corp.;
- Contracts#1, 2, 3, 4 and 5 -Provision for [BFC] to pay for the lost and damaged equipment furnished them by the [Form-Eze]; and
- Contract #1 - Provision in the Contract to include the P75 per contact sq.m. for labor guarantee.
FINAL AWARD BY CIAC
On 7 December 2007, the CIAC Arbitral Tribunal rendered a Final Award in favor of Form-Eze. The dispositive portion reads:
WHEREFORE, award is hereby made in favor of Claimant and against [BFC], ordering the latter to pay the former the following amounts:
a) On Contracts No. 1 Less: Payments already made TOTAL
b) On Contract No. 2 Less: Payments already made Less: Cost of labor TOTAL
c) On Contract No.3 Less: cost of labor On Letter Agreement of January 5, 2008 to December 8, 2007 IN SUM THE FOLLOWING AWARDS ARE MADE: Contract No. 1 Contract No. 2 Contract No. 3 Letter Agreement of January 5, 2007 GRAND TOTAL The Tribunal further awards in favor of [Form-Eze] and against [BFC] and [Pineda] who are ordered, jointly and severally to pay [Form Eze] P300,00.00 as attorney's fees, and to indemnify [Form-Eze's] cost of arbitration paid to CIAC.
The Tribunal likewise disposes of the remaining issues as follows:
a)
The claims under Issues No. 5 and 6 for reformation of Contracts No 1, 2, 3, 4 and 5 are denied for lack of merit.
- 1 Rollo, Vol. I, pp. 131-151; Penned by Associate Justice Marlene Gonzales-Sison with Associate Justices Fernanda Lampas Peralta and Florito S. Macalino concurring.
- 2 Id. at 153-157.
- 3 Id. at 1596-1600.
- 4 Id. at 161.
- 5 Id. at 162.
- 6 Id. at 163.
- 7 Id. at 164.
- 8 Id. at 165.
- 9 Id. at 166.
- 10 Id. at 167.
- 11 Id. at 158.
- 12 Id. at 160.
- 13 Id. at 195-196.
- 14 Id. at 250-251.
- 15 Id. at 253-254.
- 16 The CIAC Arbitral Tribunal corrected Issue No. 6 in the TOR upon BFC's motion.
- 17 Rollo, Vol. I, pp. 252-253.
- 18 Id. at 2157-2159.
- 19 Rollo, Vol. II, pp. 2179-2181.
- 20 Id. at 3368-3370.
- 21 Rollo, Vol. I, pp. 123-124.
- 22 716 Phil. 788 (2013).
- 23 Id. at 802-803.
- 24 Ibex International, Inc. v. Government Service and Insurance System, 618 Phil. 304, 312-313 (2009) citing Uniwide Sales Realty and Resources Corp. v. Titan-Ikeda Construction and Dev't. Corp., 540 Phil. 350, 360-361 (2006).
- 25 Rollo,Vol. I, pp. 2137-2139.
- 26 See BFC's Memorandum, rollo, Vol. II, p. 3382.
- 27 Rollo, Vol. I, p. 204.
- 28 Filinvest Land, Inc. v. Backy, 697 Phil. 403, 412-413 (2012).
- 29 Multi-ventures Capital and Management Corp. v. Stalwart Management Services, Corp., 553 Phil. 385 391 (2007).
- 30 Id.
- 31 Id.
- 32 Rollo, Vol. I, pp. 198-200.
- 33 Rollo, pp. 861-862; TSN, 13 August 2007.
- 34 See Judicial Affidavit of Mr. James W. Franklin; rollo, pp. 287-288.
- 35 Rollo, Vol. I, p. 482.
- 36 Id. at 204.
- 37 Id. at 324-325, 330 and 334.
- 38 Id. at 387. Judicial Affidavit of Mr. Clemente.
- 39 Filipinas (Pre-Fab Bldg.) System, Inc. v. MRT Dev 't. Corp., 563 Phil. 184, 218 (2007).