Section 1

Appropriations

Section 1.

Appropriations. — The sum of twenty-two billion four hundred sixty-seven million six hundred eight thousand pesos (P22,467,608,000) is hereby appropriated as supplemental appropriations for the FY 2014 Budget.

Section 2

Payment for the Implementation of Urgent Projects

Section 2.

Payment for the Implementation of Urgent Projects. — The sum of twenty-two billion four hundred sixty-seven million six hundred eight thousand pesos (P22,467,608,000) is hereby appropriated to fund urgent and important projects which cannot be funded by savings or through the Unprogrammed Fund and are not funded under Republic Act No. 10633 or the FY 2014 General Appropriations Act (GAA). The government agencies or Government-Owned and -Controlled Corporations (GOCCs), projects or programs, and amounts covered are as follows:

Government Agency/GOCC/ Special Purpose Fund

Project/Program

Amount

1.

Department of Finance — Bureau of the Treasury

Additional Capital Outlay and MOOE for the implementation of the Treasury Single Account

P803,380,000

2.

Department of Finance — Bureau of the Treasury

Budgetary Shortfall for Transaction Fees and Charges as a Result of the Implementation of the Treasury Single Account

100,407,000

3.

Department of Environment and Natural Resources — Office of the Secretary

Payment for the Actual Services Rendered by the 294 Hired Bantay Gubat

11,176,000

4.

Department of Finance — Office of the Secretary

Phase 2 of the Renovation of DOF — OSEC Property

32,224,000

5.

Department of the Interior and Local Government — Bureau of Fire Protection

Transition Investment Support Plan — ARMM Procurement of 33 Firetrucks

199,167,000

6.

Department of the Interior and Local Government — Philippine National Police

Operational Transformation Plan for the Philippine National Police

2,833,282,000

7.

Department of Justice — Office of the Secretary

Transfer of Quezon City Prosecutors and Public Attorney—s Offices, Including the Provision for Electrical Connection, Water Connection, PABX Telephone Rack Installation and Structured Cabling

10,500,000

8.

Department of Science and Technology — Information and Communications Technology Office

Acquisition of 15,000 Units of Personal Computers

300,000,000

9.

Department of Public Works and Highways — Office of the Secretary

Obligations Arising from Implemented Infrastructure Projects

1,902,743,000

10.

Department of Public Works and Highways — Office of the Secretary

Completion of Development Assistance to the Province of Quezon

240,000,000

11.

Department of Public Works and Highways — Office of the Secretary

Construction of the New Bohol Provincial Capitol to Replace Condemned Building

350,000,000

12.

Department of Public Works and Highways — Office of the Secretary

Retrofitting of the Presidential Management Staff Office Building

210,000,000

13.

Department of Social Welfare and Development — Office of the Secretary

Updating of the National Household Targeting System for Poverty Reduction (NHTS-PR)

1,942,521,000

14.

Department of Social Welfare and Development — Office of the Secretary

Emergency Shelter Assistance for Victims of Typhoon Yolanda

2,084,480,000

15.

Department of Transportation and Communications — Office of the Secretary

Metro Rail Transit 3 Rehabilitation and Capacity Extension, Including Total Replacement of the Existing Signaling System and Rehabilitation of Escalators and Elevators

1,207,163,000

16.

House of Representatives

Completion of the Legislative Library and Archives Building/Congressional E-Library

250,000,000

17.

House of Representatives

Expenses of the Ad-Hoc Committee on Bangsamoro Basic Law and Printing of the 2015 General Appropriations Bill

70,169,000

18.

Department of Transportation and Communications — Light Rail Transit Authority

Rehabilitation of Light Rail Transit Line 1 and Line 2

727,690,000

19.

Department of Transportation and Communications — Mactan-Cebu International Airport Authority

Construction of Mactan-Cebu International Airport Presidential and Dignitaries (PAD) Lounge Building

118,559,000

20.

Department of Environment and Natural Resources — Environmental Management Bureau

Remediation of the San Mateo Sanitary Landfill

178,005,000

21.

National Electrification Administration

Installation of 10-Megavolt Amperes Substation in Sto. Domingo, Albay

32,552,000

22.

National Housing Authority

Construction of 27,313 Units of Permanent Housing for Victims of Typhoon Yolanda

7,999,978,000

23.

National Housing Authority

Implementation of the North Triangle Relocation Project

286,702,000

24.

Philippine Coconut Authority

Coconut Scale Insect Emergency Action Plan

340,345,000

25.

Philippine Fisheries Development Authority

Construction of Fishport, Lighthouses and Seawalls

196,385,000

26.

Philippine Institute for Development Studies

Provision for Rent of Office Space During Pendency of Construction of PIDS— New Building

40,180,000

Total

P22,467,608,000

Section 3

Use and Release of Funds

Section 3.

Use and Release of Funds. — The amount appropriated shall be released by the Department of Budget and Management (DBM) to the implementing agencies in accordance with budgeting, accounting and auditing laws, rules and regulations: Provided, That the Department of Social Welfare and Development (DSWD) shall develop a uniform formula or parameter for the fair and equitable distribution of the Emergency Shelter Assistance Fund for the victims of Typhoon Yolanda.

Section 4

Section 4.

Applicability of General and Special Provisions in the FY 2014 General Appropriations Act. — The amounts herein appropriated shall be used for the purposes indicated and subject to the relevant special and general provisions under Republic Act No. 10633 or the FY 2014 GAA.

Section 5

Availability of Appropriations

Section 5.

Availability of Appropriations. — The appropriations authorized in this Act shall be available for release and obligation for the purposes specified for one (1) year from the date of the effectivity of this Act.

Section 6

Transparency Provisions

Section 6.

Transparency Provisions. — The concerned implementing agencies shall ensure that the details of projects, such as the name of contractors or suppliers and corresponding amount paid, are included as part of the information posted on their transparency seals required under Section 91 of the General Provisions under Republic Act No. 10633 or the FY 2014 GAA.

Section 7

Separability Clause

Section 7.

Separability Clause. — If, for any reason or reasons, any part or provision of this Act shall be declared as unconstitutional or invalid, the other parts or provisions hereof which are not affected thereby shall continue to be in full force and effect.

Section 8

Effectivity

Section 8.

Effectivity. — This Act shall take effect immediately upon its publication.

Approved,

(Sgd.) FRANKLIN M. DRILON President of the Senate

(Sgd.) FELICIANO BELMONTE JR. Speaker of the House House of Representatives

This Act which originated in the House of Representatives was finally passed by the House of Representatives and the Senate on December 17, 2014.

(Sgd.) OSCAR G. YABES Secretary of Senate

(Sgd.) MARILYN B. BARUA-YAP Secretary General House of Representatives

Approved:

DEC 23 2014

(Sgd.) BENIGNO S. AQUINO III President of the Philippines